Génie Hydro | Consulting en Ressources Hydriques

Hagoscon Logo : Une représentation stylisée du nom de l'entreprise, avec des couleurs vibrantes et un design moderne. Génie Hydro offre des services de consulting en génie hydrologique, gestion des ressources en eau, structures hydrauliques, et plus encore.
Chêne-Bougeries
Genève, Suisse
Mon-Fri
09:00 - 17:00
+41 79 392 2970

irrigation project

Projet d'irrigation de surface
Client Bureau régional (Gov)
Location Adi Gudem, Tigray, Ethiopia
Scope Of Work Construction de canaux et de structures de chute
Schedule 1996-1997
Architect SAERT (Semi Gov org)

Project Detail

Adigudem Surface Irrigation Project (Gumselasa dam)

In 1996,  the Adigudem dam had already been completed and the next assignment was to construct the irrigation canals at the downstream of the dam. Figure  1 shows the Adigudem surface irrigation project (Gumselasa dam).

  Figure  1 Adigudem surface irrigation project (Gumselasa dam), Tigray, Ethiopia

 

Enterprise:  Sustainable Agriculture and Environmental Rehabilitation in Tigray Region (SAERT). A semi-governmental institute and its main office were located at Mekele city, in the northern region of Ethiopia.

Period of construction: February 1996 – November 1996

Based on the details provided from the land survey,  the size of the farmland was 136ha. The method of irrigation designed for this farm was surface irrigation that comprised of primary/principal canal (trapezoidal), the secondary canal (trapezoidal), and tertiary canals (trapezoidal). The primary and secondary canals were the main conveyors of water from the dam to the farming ground and hence the secondary canals were located at the left and right extreme boundaries of the farmland. The tertiary canals were designed to distribute water into the side furrows and consequently, it originates roughly perpendicular to the secondary canals towards the field as indicated in Figure 1. The existing waterway in the middle of the farm utilized as natural drainage of excess water to the far downstream.

The canals incorporated 400 concrete drop structures (canal falls) with a size of around 1-1.7 m height and 90-1.20cms width and 0.3m thickness. The downstream and upstream side of the drop structures have actually simple stone aprons (without mortar). There were two large drop structures with stilling basins at the downstream side and concrete apron at the upstream side.

Figure 2 helps to conjure up the drop structure constructed at the Adigudem site. The image presented here is not the actual picture taken at the Adigudem irrigation site but a portrayal to visualize the structures constructed at the project site (similar to these drop structures).

 

There were three culverts; two of them were placed along the route and facilitate or used as a passage to tractors to the other side of the farm and the third culvert utilized to link up the primary canal and the right side secondary canal.

The canals were dug out by local communities hardly with any assistance of machinery.

Turnouts (Division box)

There were several turnouts (diversion boxes with small gates) at the junction of secondary and tertiary canals. An illustration of the division box shown in Figure 3 and 4 utilized to demonstrate the actual turnout at the Adigudem irrigation project.

 

Figure 3 Division box /turnout (FAO)

Figure 4 Turnouts (FAO)

 

Stilling Basin

There were two Large drop structures that have stilling basin with an approximate size of 3m* 2m*0.4m. Figure 5 shows a typical example of a stilling basin.

Figure 5 Typical Example of a stilling basin (www.nzdl.org)

Project Cost

The cost of the project can certainly be roughly estimated employing the cost incurred on the 1000 laborers, two tractor operators, two paid foremen, an engineer, a co-engineer and a paid local community mobilizer. The period of construction lasts around 10 months. The cost incurred on essence and tractor maintenance, sand, cement, stone, and other design and supervision costs are not included in this estimation.

Hence, the cost incurred without including the material costs is well over : 3,500,000 Birr (rate 1$ to7birr) = 500, 000$.

The Role of The Site Engineer

The responsibility of the site engineer was, transmitting the layout design from the paper to the ground using surveying instruments (theodolite), identifying the placement of the drop structures along the canals, and plus monitoring the construction process.

The project was successfully completed and enabled the local community of Adigudem to produce their vegetables and crops throughout the year. The farm exists until now. Nevertheless, owing to the piling up of silt at the reservoir, the quantity of water that could be retained behind the dam is drastically dropped. Subsequently, this trims down the volume of water which can be used for irrigation application.

Points to Highlight 

Location: Adigudem, Tigray region, Northern  Ethiopia

Done solely by human labor (no canal digging machines used)

Irrigation area:  136 ha of land

Earth Canals: primary, secondary, and tertiary canals

Drop structures:  400 (~1.7m*1.20m* 0.3m )

Culverts:  3

Turnouts (diverting box with gates):  numerous

Grand drop structure with stilling basin:  2, (~size 3m* 2m*0.4m)

 

 

 

 

 

This function has been disabled for Group H&S

Domaine d'expertise

  Création de groupe professionnel