Génie Hydro | Consulting en Ressources Hydriques

Hagoscon Logo : Une représentation stylisée du nom de l'entreprise, avec des couleurs vibrantes et un design moderne. Génie Hydro offre des services de consulting en génie hydrologique, gestion des ressources en eau, structures hydrauliques, et plus encore.
Chêne-Bougeries
Genève, Suisse
Mon-Fri
09:00 - 17:00
+41 79 392 2970

Dam Construction

Barrage de terre à petite échelle (17 m de hauteur)
Client Bureau régional
Location Halhal, Eritrea
Scope Of Work Conception et construction
Schedule 2007-2008
Architect Ministère de l'Agriculture

Project Detail

Halhal Small Scale Earth Dam Construction ( Dam Mikilim)

In 1997, a dam was conceived by the Ministry of Agriculture (MOA) to be built at  Halhal village. The intention was to conserve water for irrigation purposes. Subsequently, the village farm can benefit directly from withdrawing water from the reservoir or from the replenished groundwater system.

Period of construction: from February 1997 – June 1997 almost 4 months of intense work.

Location: Halhal village, Anseba region of Eritrea. Figure 1 is a birds-eye view of the reservoir.

Figure 1 Halhal small scale earth dam,  Mikilim Dam (google image)

Enterprise: Ministry of Agriculture (MOA), Asmara, Eritrea. It was a governmental organization comprised of six regional and numerous sub-regional offices. The principal office nestled at Asmara, Capital of Eritrea.

Method of Construction: all sorts of heavy equipment utilized such as rollers, loaders, dozer, and grader. Moreover, loading trucks and pickup vehicles were utilized as a mode of transport.

The responsibility here was to construct the dam as well as monitor other small diversion structures at the surrounding regions such as the Asmat area where a small weir structure was built to redirect flush flood into a basin irrigation system. Figure 2 shows the Asmat irrigation project survey.

  Figure 2 Photo taken at Asmat irrigation project, 1997

The  Halhal dam was designed to be 17m high, crest length 65m, crest width  5m, and the bottom width about 90m. The core body of the dam was built with clay soil and the two opposite outer body surfaces were packed with dirt dug out from the reservoir area. The upstream and downstream surface slop were 1:3 and 1:2 respectively. Both sides were covered with stone rip-rap. Moreover, the downstream side has a berm in the middle.

Gravel and Sand Filter

The downstream side toe of the dam has a sand and gravel filtration system that can help to discharge water from the phreatic line safely. Figures 3  and 4 show a typical earth dam profile and the gravel filter lying process at Halhal dam.

Figure 3   Typical example of earth dam profile

 

Figure 4 Gravel filter lying, Halhal

Spillway

The spillway was merely a dugout; it has around 10m width and around 1.5m depth. The length of the spillway extends to the downstream side of the existing river course as indicated in Figure 1. Consequently, the freeboard level of the dam was at level 15.5m from the bottom, or in other terms, the maximum depth of water was equivalent to 15.5m. The fetch length of the reservoir stretched out greater than 120m in the direction of the upstream reservoir boundary.

Outlet Structure

The outlet was made from a regular concrete pipe nevertheless protected or covered by a reinforced concrete cover. There were around 11 collars ( 7ms distance between each collar)  along the pipe to help minimize creeping water.

Figure 5 illustrates or represents the type of collars used at Halhal dam; however, the image is downloaded from the internet simply to demonstrate the type of collars used.

 

Figure 5 Seepage protection collar

The outlet structure at Halhal shown in Figures 6 and 7

                          Figure 6 Halhal outlet structure (photo taken just after the construction ended)

The outside end of the outlet structure constructed with a metal pipe that links the valve and the concrete pipe is shown in Figure 7.

 

Figure 7 Valve and concrete pipe connector used at Halhal dam

Foundation

The foundation at the central axis of the dam was dugout and filled up with clay soil up to the freeboard level. Figure 8 shows the construction process of the dam at Halhal.

Figure 8 Construction of Halhal earth dam (Dam Mikilim)

Compaction

The compaction was taken care of with two rollers and the methodology applied was simply rolling 4 times back and forth on  0.3m thick dirt while pouring water on it. The dozer disperses the dirt along the surface, and then the rollers roll over it. Figure 9 shows the compaction process of the Halhal dam.

Figure 9 Compaction of Halhal dam

Hydrological Studies

The hydrological study of the dam was implemented roughly using empirical formulas. 10% of the annual rainfall considered being a runoff and then from this, the volume can be easily calculated multiplying the runoff depth with the area of the catchment (Watershed).

Project Cost

As it was a government project, the cost incurred in the project could be retrieved from the government bureau. Nevertheless, it is possible roughly to evaluate the cost incurred based on the number and type of machinery utilized as well as personals took part in the project during the given period of construction.

The number of machinery worked 8hrs per day throughout weekdays encompass two compactors, a loader, an excavator, two dozers, a grader,  water tank trucks, two pickup cars, two loading trucks. The personals were a trained engineer, a foreman, two machinery foremen, and operators for each individual machine highlighted above. Additionally, around twenty laborers and craftsmen took part in the construction process as well.

Consequently, the cost of construction without including the materials utilized such as essence, cement, sand,  reinforcement bar, concrete pipes, and vehicle repairs and maintenance etc.. Simply based on the monthly earnings of the personals, the expense gets well over ~1 million Nakfa ($71, 428.57 ).

The Role of the Site Engineers

The tasks of the site engineer were regulating the concrete mix and the soil type used, assisting the foremen interpreting drawings, compaction control, organizing machinery and construction materials, helping on the reinforcement bar schedule, transmitting the design from the paper to the ground, guiding the excavation and supervising the construction in general based on the plan provided.

The number of skilled and non-skilled personals took part in the construction were the following: one trained engineers, carpenters, and masons as well as non-skilled laborers. Furthermore, a large number of machinery group members and machinery foremen were involved in the construction.

Points to Highlight

Location: Halhal, Anseba region, Eritrea

Type: Earth dam

Height:  ~    17m

Crest Width: ~   5m

Crest length ~  65m

Spillway (Earth) width: 10m

Dam profile Slope: U/S 1:3 and D/S 1:2

Link to the current status of the dam

 

This function has been disabled for Group H&S

Domaine d'expertise

  Création de groupe professionnel